Centrifugal Versus Positive Displacement Pumps
October 31, 2026
When Should Fire Hoses Retire? A Site Decision
November 4, 2026How to Align Rotating Machinery Correctly
A pump set that appears to run normally can still be consuming bearings, damaging seals and transferring avoidable load into its driver. To align rotating machinery correctly is not a finishing task after installation. It is a controlled maintenance activity that protects availability, energy efficiency and safety across pumps, compressors, generators, fans, gearboxes and marine auxiliary systems.
For operations teams, the objective is not simply to achieve a favourable reading on an alignment instrument. The objective is to establish the correct shaft relationship at operating condition, while accounting for the machine base, connected pipework, temperature change and the condition of the coupling. That distinction matters in power generation, offshore, marine and process environments, where an unplanned shutdown may affect production, safety systems or vessel operations.
What correct shaft alignment means
Shaft alignment is the adjustment of two coupled machine shafts so their centre lines meet within the tolerances specified for the equipment and its expected operating conditions. Misalignment commonly occurs in two forms: angular misalignment, where shaft centre lines meet at an angle, and parallel or offset misalignment, where centre lines remain apart.
Most installations contain a combination of both. A flexible coupling can accommodate limited movement, but it should not be used to conceal poor alignment. Couplings are designed to transmit torque and manage defined operational movement. They are not a substitute for sound installation practice.
The practical consequences of misalignment are familiar: elevated vibration, high bearing temperatures, premature seal failure, coupling wear, loosened fasteners and repeat maintenance intervention. On a diesel-driven pump or critical generator set, these symptoms can be mistaken for a component fault when the underlying cause is an incorrect machine position.
Prepare before you align rotating machinery
Alignment results are only as reliable as the condition of the machine train. Beginning measurements before basic checks are complete often produces readings that cannot be repeated once the equipment is tightened, connected or brought to temperature.
Confirm isolation and mechanical condition
Apply the site isolation procedure before guards are removed or shafts are turned. Verify that the driver and driven equipment are properly secured, coupling components are suitable for inspection, and shafts can be rotated safely. Check bearings, mounting bolts, coupling elements and baseplate condition. Excessive bearing clearance, damaged coupling hubs or loose foundations can make precise alignment impossible.
Inspect the foundation and baseplate for corrosion, cracked grout, distorted soleplates and signs of movement. On marine installations, structural flexing and machinery seating condition require particular attention. A machine may have been aligned correctly at commissioning yet move over time because its support arrangement has changed.
Eliminate soft foot first
Soft foot exists when one or more machine feet do not sit evenly on the mounting surface. Tightening the hold-down bolts pulls the machine frame into distortion, changing shaft position and creating stress through the casing.
Check each foot using a suitable measurement method and correct the condition before taking final alignment readings. Clean mounting surfaces thoroughly and use purpose-made, clean shims of appropriate size and material. Avoid stacked, damaged or excessively small shims, which can settle or introduce instability. If correction requires substantial shimming, investigate the base condition rather than treating shims as a permanent cure for a poor foundation.
Remove external forces
Pipe strain is a frequent source of lost alignment. Pipework connected to a pump casing should be independently supported so that connecting or disconnecting flanges does not move the machine. Check movement at the coupling while pipe flanges are loosened in accordance with the maintenance procedure. If the shaft position changes, the pipework requires correction before alignment can be finalised.
The same principle applies to electrical conduit, hydraulic lines, exhaust systems and ancillary brackets. Any connected service capable of exerting a load on the machine can alter the final result.
Select a method that suits the equipment
Straightedge and feeler-gauge checks remain useful for rough positioning and initial installation work, particularly where access is limited. However, they do not provide the accuracy or recorded data expected for critical machinery.
Dial indicators can achieve accurate results when used by experienced personnel and when bracket sag, shaft run-out and measurement geometry are controlled. They remain a valid option for many maintenance teams, but setup and interpretation take time.
Laser shaft-alignment systems provide fast, repeatable measurement of horizontal and vertical offset and angularity. They also guide live corrections and produce records that can support maintenance history, commissioning documentation and failure investigation. For high-value or safety-critical equipment, this traceability is often as valuable as the speed of the measurement.
The right method depends on coupling type, shaft diameter, machine speed, access, required tolerance and the competence of the personnel carrying out the work. Instrument accuracy does not replace mechanical judgement. A laser system will identify movement precisely, but it cannot determine whether that movement is caused by soft foot, pipe strain or an unstable base unless the technician investigates the installation.
Set alignment targets for operating conditions
Cold alignment is not always the final target. Drivers and driven machines move as they warm up, particularly where a turbine, engine, compressor or process pump operates at significantly different temperatures from its surroundings. This thermal growth can change both vertical and horizontal shaft position.
Use original equipment manufacturer data where available, together with operating temperature, machine geometry and historical vibration information. In some trains, the driver must be positioned deliberately low or high when cold so that the shafts align at normal operating temperature. In others, thermal movement is negligible and a conventional cold target is appropriate.
Do not apply generic tolerances without considering speed and duty. Higher-speed equipment generally requires tighter alignment control. Equally, a low-speed machine with a rigid coupling, heavy process piping or a history of seal failures may justify a more exacting target than a basic tolerance table suggests.
Make corrections in a controlled sequence
Alignment corrections should be deliberate and documented. Adjust the movable machine wherever practical, rather than disturbing the machine fixed by process connections or foundation design. Vertical corrections are normally made with shims; horizontal corrections are made by controlled lateral movement using jacking bolts or suitable positioning tools.
After each adjustment, tighten hold-down bolts to the specified condition and remeasure. A reading taken with loose bolts is not a final reading. Check that the movement made at the feet corresponds with the planned correction at the coupling. If results move unpredictably, stop and reassess soft foot, base stability, bolt condition and external forces.
Once the target is achieved, reinstall coupling elements and guards in line with the manufacturer’s requirements. Confirm bolt torques, lubrication requirements and coupling clearances. The machine should then be monitored during return to service for vibration, temperature and leakage. Alignment is complete only when the equipment performs as expected under load.
Build alignment into planned reliability work
Reactive alignment after a bearing or seal failure is sometimes unavoidable, but planned checks are more cost-effective. Include alignment verification after pump overhaul, motor replacement, baseplate repair, piping modification, vessel dry-docking, machinery relocation or any event that may have disturbed the train.
Recorded as-found readings are particularly useful. They reveal whether a machine has moved gradually, whether thermal targets remain appropriate and whether repeated failures correspond with a recurring alignment pattern. This information helps maintenance leaders prioritise root-cause correction rather than repeatedly replacing components.
For project procurement and engineered supply, alignment should also be considered before equipment arrives on site. Compatible couplings, correctly specified baseplates, reliable mounting hardware, suitable shims and access for measurement tools reduce installation risk. SFRM supports this wider equipment view by connecting component supply and technical requirements with the realities of field operation.
A well-aligned machine train will still require proper lubrication, balanced rotating parts and sound operating practice. Yet when vibration rises or seals fail without an obvious cause, return first to the fundamentals: verify the base, remove external loads, account for operating movement and measure the shaft relationship with a method suited to the duty. That disciplined approach gives maintenance teams a practical basis for longer equipment life and more dependable service.